An project will reuse an existing space. The area of retained components is larg

[复制链接]

262

主题

0

好友

33

积分

管理员

Rank: 9Rank: 9Rank: 9

跳转到指定楼层
楼主
发表于 2012-8-4 17:13:07 |只看该作者 |正序浏览
试卷: LEED AP ID+C 模拟试卷B[查看]
An project will reuse an existing space. The area of retained components is larger than the completed design area. The project space has the following finished surface areas:

Element ; Prior Condition Area (sf) ; Retained Area(sf)
Finished ceiling ; 20,000 ; 20,000
Finished floors ; 20,000 ; 10,000
Interior wall partitions ; 10,000 ; 10,000
Exterior windows ; 2,000 ; 0
Exterior doors ; 1,000 ; 0
A: 74%
B: 80%
C: 77%
D: 75%

参考答案: B

本题解释:
Reference: Materials and Resources Credit Building Reuse - Maintain Interior Nonstructural Component

The equation to determine the maintained area is:

Interior nonstructural component reuse % =
(Total retained component area (sf) / Larger of prior condition OR completed design area (sf)) X 100 (pg 225 in the reference guide)

The exterior windows and doors do not count towards this credit and are excluded.

Prior condition area = 20,000 + 20,000 + 10,000 = 50,000 sf
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2025-4-6 03:35 , Processed in 0.114514 second(s), 26 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部