试卷: LEED AP ID+C 模拟试卷B[查看] A tenant space is chosen that has an underground stormwater treatment system that is not visible. Building management has documentation that total suspended solids (TSS) are being reduced by 90%. What additional step (if any) is needed to earn Sustainable Sites Credit, Site Selection, Stormwater Design Quality Control?
A: The project must show at least 40% of the average annual site area’s total phosphorus (TP) is being removed B: No additional step is needed C: Bioswales or a retention basin must be installed D: The project must show the pre-development runoff rate is 25% less than the annual onsite stormwater load 参考答案: A
本题解释: Reference: Sustainable Sites Credit, Site Selection, Stormwater Design-Quality Control, Requirements
For this path TSS must be reduced by at least 80% and TP must be reduced by at least 40%. |
|