A project site has been chosen where the prior project team of the building had

[复制链接]

262

主题

0

好友

33

积分

管理员

Rank: 9Rank: 9Rank: 9

跳转到指定楼层
楼主
发表于 2012-8-3 09:23:20 |只看该作者 |正序浏览
试卷: LEED AP ID+C 模拟试卷B[查看]
A project site has been chosen where the prior project team of the building had restored 100% of the site with native vegetation. The building site was a former amusement park. The building site requires no irrigation. What credits and points can this project earn?
A: 5 points for Sustainable Sites Credit, Site Selection
B: 4 point for Sustainable Sites Credit, Site Selection and 1 point for Innovation in Design Credit, Innovation in Design
C: 4 point for Sustainable Sites Credit, Site Selection
D: 2 points for Sustainable Sites Credit, Site Selection and 1 point for Innovation in Design Credit, Innovation in Design

参考答案: A

本题解释:
Reference: Sustainable Sites Credit, Site Selection, Other Quantifiable Environmental Performance, R

The project can earn 1 point for Site Selection Path 12 by achieving \'other quantifiable environmental benefits\'. In this case the project building had restored 100% of a previously developed site.

The project can earn 4 points for Sustainable Sites Credit, Site Selection, Water Efficient Landscaping-No Potable Water Use or No Irrigation for using no irrigation.
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2025-4-6 04:04 , Processed in 0.075529 second(s), 26 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部