试卷: LEED AP ID+C 模拟试卷A[查看] The design team is documenting the basis of design for fundamental commissioning. Which items are not required in the basis of design? A: Load and climatic assumptions for design decisions B: Architectural drawings of system locations C: Design assumption for occupancy D: Standards, including applicable codes, guidelines, etc. 参考答案: B
本题解释: See Energy and Atmosphere Prerequisite, Fundamental Commissioning of Building Energy Systems, Timeline, Step 2, Basis of Design
The basis of design includes primary design assumptions (occupancy, climatic assumptions), standards, and narrative descriptions. Architectural drawings are not included. |
|