LEED GAP

 找回密码
 立即注册

QQ登录

只需一步,快速开始

搜索
查看: 424|回复: 0
打印 上一主题 下一主题

Question 1 During fundamental commissioning, who is in charge of developing the

[复制链接]

1759

主题

1

好友

5674

积分

管理员

Rank: 9Rank: 9Rank: 9

跳转到指定楼层
楼主
发表于 2012-7-29 10:46:28 |只看该作者 |正序浏览
试卷: LEED AP ID+C 模拟试卷A[查看]
During fundamental commissioning, who is in charge of developing the basis of design?
A: Owner
B: Commissioning authority
C: Owner and commissioning authority
D: Design team

参考答案: D

本题解释:
See Energy and Atmosphere Prerequisite, Fundamental Commissioning of Building Energy Systems
The correct answer choice comes from the section titled Step 2, Basis of Design. The design team documents the basis of design, which is the information needed to accomplish the owner's project requirements. These include:

-system descriptions
-IEQ criteria
-design assumptions
-references to codes, standards, regulations, and guidelines

The owner is in charge of developing the OPR, owner's project requirements.
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2024-12-23 04:55 , Processed in 0.077189 second(s), 26 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部