试卷: LEED AP ID+C 模拟试卷C[查看] A project is purchasing salvaged bricks from a local company that sourced the bricks from local buildings that are scheduled for demolition. The cost of the bricks was $175 per ton. The company received a 10% off discount (excluding shipping) by paying within 15 days. The project will use the bricks to make the floor of the lobby area and will purchase 10 tons of bricks. What dollar value should be used for the Materials and Resources Credit, Materials Reuse calculation?
A: $1,975 B: $1,575 C: $1,750 D: $2,150 参考答案: B
本题解释: Any discount has to be reflected in the price as well.
($175/ton X 10 tons) - ($175/ton X 10 tons X 10% discount) = $1,575 |
|