试卷: LEED AP ID+C 模拟试卷A[查看] At the beginning of the integrated design process the project team has come together to discuss how the project can earn LEED certification. Which critical tasks should be addressed in this meeting? A: The use of certified wood B: Commissioning C: Parking capacity D: Access to public transportation 参考答案: B
本题解释: Commissioning is the process used to verify and ensure that fundamental building elements and systems are designed, installed, and calibrated to operate as intended. Since commissioning is a prerequisite for certification, it should be addressed as early as possible in a project.
Other important design decisions that should be made early on include site selection, daylighting strategies, and water usage. |
|