SS Credit 4.1: Alternative Transportation—Public Transportation Access
6 Po

[复制链接]

1759

主题

1

好友

5674

积分

管理员

Rank: 9Rank: 9Rank: 9

跳转到指定楼层
楼主
发表于 2012-8-14 14:20:30 |只看该作者 |倒序浏览
试卷: SS 可持续场地[查看]
SS Credit 4.1: Alternative Transportation—Public Transportation Access
6 Points
Intent
To reduce pollution and land development impacts from automobile use.

Requirements
OPTION 1. Rail Station Proximity
Locate the project within 1/2-mile walking distance (measured from a main building entrance) of an existing or planned and funded commuter rail, light rail or subway

OPTION 2. Bus Stop Proximity
Locate the project within 1/4-mile walking distance (measured from a main building entrance) of 1 or more stops for 2 or more public, campus, or private bus lines usable by building occupants.

Potential Technologies & Strategies
Perform a transportation survey of future building occupants to identify transportation needs. Locate the building near mass transit.

SSC 4.1: 替代交通—接入公共交通
6 分

目的
减少因机动使用造成的环境污染和土地开发影响。

要求
选项1. 接近轨道交通站点
建筑1/2英里(804米)的步行距离范围内(由建筑主入口起算)有或规划中的往返轨道、轻
轨、地铁线。
或者
选项2. 接近公交车辆站点
建筑1/4英里(402米)的步行距离范围内(由建筑主入口起算)有1个或多个公交站点及2个
以上公共汽车、校车以及建筑用户可用的私人公交班次。

技术措施和策略
对未来建筑用户进行交通调研并确定交通需求量。建筑尽量选址在公共交通线附近。

分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2024-12-26 22:13 , Processed in 0.077027 second(s), 26 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部