试卷: LEED AP BD+C模拟题A[查看] What is true about the timing of commissioning as it relates to a building flush-out? A: Commissioning can occur during the flush-out if it does not introduce any additional contaminants into the building B: Commissioning must be completed before the building flush-out C: Commissioning can only occur at the same time as a flush-out if an occupied flush-out is being performed D: Commissioning cannot begin until after the building flush-out has been completed 参考答案: A
本题解释: Notes:
Reference: Indoor Environmental Quality Credit, Construction Indoor Air Quality Management Plan-Before Occupancy, Implementation Commissioning can occur during the flush-out if it does not introduce any additional contaminant into the building. |
|