A new mixed-use building project in an urban area has a site area of 800,000 sq. ft. A zoning
ordinance exists, but there is no requirement for open space. How big must the open space be to
achieve an Innovation Point for Sustainable Sites Credit, Site Development-Maximize Open
Space?
A: 160,000
B: 200,000
C: 320,000
D: 240,000

参考答案: C

本题解释:
Notes:
Remember that exemplary performance is part of the Innovation in Design section.
This project is for an urban area where zero open space is required, so the open space must be
equal to 40% of the site area to earn an Innovation Point.


800,000 sq. ft. * 0.40 = 320,000 sq. ft.
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏1
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2024-12-25 11:46 , Processed in 0.110456 second(s), 26 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部