试卷: LEED AP BD+C模拟题B[查看] A project design includes an active wastewater treatment system to treat 75% of
wastewater onsite to achieve Water Efficiency Credit, Innovative Wastewater Technologies.
This design decision will impact which project area? A: Sustainable Sites Credit, Heat Island Effect-Roof B: Water Efficiency Credit, Process Water Use Reduction C: Energy and Atmosphere Prerequisite, Fundamental Commissioning of Building Energy Systems D: Sustainable Sites Credit, Stormwater Design-Quantity Control 参考答案: C
本题解释: Notes:
An active wastewater treatment system uses additional energy and requires commissioning, and
also measurement and verification. Please note that wastewater is different than stormwater. This
question specifically asks about wastewater treatment. |
|