LEED GAP

 找回密码
 立即注册

QQ登录

只需一步,快速开始

搜索
查看: 553|回复: 0
打印 上一主题 下一主题

A retail project has an overall budget of $6,450,000. The materials cost on the

[复制链接]

262

主题

0

好友

33

积分

管理员

Rank: 9Rank: 9Rank: 9

跳转到指定楼层
楼主
发表于 2012-8-12 17:40:37 |只看该作者 |倒序浏览
试卷: LEED AP ID+C 模拟试卷C[查看]
A retail project has an overall budget of $6,450,000. The materials cost on the project is $2,902,500. Here is a list of some of the materials the project team has purchased. Based on this list what percentage of material will count towards Materials and Resources Credit, Rapidly Renewable Materials?

Material Cost Weight (lbs)
Bamboo flooring $46,000 ; 1500;
Wool carpeting $30,000 ; 800;
Sunflower seed board Panels $5,000 ; 300;
Certified Wood $50,000 ; 10,000;

A: 1.2%
B: 2.8%
C: 2.0%
D: 4.5%

参考答案: B

本题解释:
First calculate the materials cost:

The bamboo flooring, wool carpeting, sunflower seed board panels all qualify as rapidly renewable. See Materials and Resources Credit, Rapidly Renewable Materials, this calculation is based on cost, not volume.

$46,000 + $30,000 + $5,000 = $81,000

$81,000 / $2,902,500 = 2.8%

Certified wood will not qualify as a rapidly renewable.
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2024-12-25 22:50 , Processed in 0.079484 second(s), 26 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部