试卷: LEED AP ID+C 模拟试卷D[查看] One story of a five-story office building is being renovated for new office space. The site has a zero-lot-line and is completely paved with impervious material. The pre-development discharge rate of stormwater is 10,000 gallons. What maximum post-development discharge rate will qualify for Stormwater Management: Quantity Control? A: 8,000 gallons B: 10,000 gallons C: 7,500 gallons D: 9,000 gallons 参考答案: C
本题解释: Notes:
This site has an imperviousness greater than 50% because it is completely paved, so Option 2 must be met for the requirements. A stormwater management plan must have a 25% decrease in that volume. The pre-development discharge rate is 10,000 gallons, so the post-development discharge rate must be 7,500 gallons or less (25% less than 10,000 gallons).
|
|