A project team is attempting Indoor Environmental Quality Credit, Construction I

[复制链接]

1759

主题

1

好友

5678

积分

管理员

Rank: 9Rank: 9Rank: 9

跳转到指定楼层
楼主
发表于 2012-8-4 17:13:07 |只看该作者 |倒序浏览
试卷: LEED AP ID+C 模拟试卷A[查看]
A project team is attempting Indoor Environmental Quality Credit, Construction Indoor Air Quality Management, Before Occupancy. The contractor will be using air quality testing to determine if contaminant levels have not been exceeded. How must baseline IAQ testing be done?
A: Randomly sampling at least one sampling point per 25,000 sq. ft. of each contiguous floor area
B: Conduct one sample per air handling unit every 15 minutes during the normal operating hours
C: Conducting one sample for each 50 ft. x 50 ft. grid
D: Using air samples collected in the breathing zone over a minimum 4-hour period

参考答案: D

本题解释:
Reference: Indoor Environmental Quality Credit, Construction Indoor Air Quality Management Plan-Befo

Capture air samples in the breathing zone over a minimum 4-hour period.

Sampling should occur during normal operating hours. The HVAC system must run at normal daily start times at the minimum outside airflow rate
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2025-4-6 04:44 , Processed in 0.074592 second(s), 25 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部