A project building is 68,490 sf. A tenant has leased out 50,200 sf. The project

[复制链接]

262

主题

0

好友

33

积分

管理员

Rank: 9Rank: 9Rank: 9

跳转到指定楼层
楼主
发表于 2012-8-3 09:23:20 |只看该作者 |倒序浏览
试卷: LEED AP ID+C 模拟试卷B[查看]
A project building is 68,490 sf. A tenant has leased out 50,200 sf. The project team will install submetering equipment to measure energy use in the tenant space. The lease will not include the energy costs in the base rent. The landlord will prorate the utilities based on the tenant’s portion of the total leasable area. How many points can the project earn for Energy and Atmosphere Credit, Measurement and Verification?
A: -3-
B: -2-
C: -5-
D: -0-

参考答案: C

本题解释:
Reference: Energy and Atmosphere Credit, Measurement and Verification, Requirements

The tenant has leased less than 75% of the total space. Submetering was installed (2 points) and the energy payment is not part of the lease (3 points) so the project can earn 5 points.

When the landlord prorates the utilities base on the percent of leasable area this meets the credit requirements (see Implementation, Case 1, Payment)
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2024-12-23 09:40 , Processed in 0.073208 second(s), 26 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部