试卷: LEED AP ID+C 模拟试卷B[查看] What project area does not require a baseline analysis?
A: Light pollution reduction B: Water use reduction C: Fundamental building commissioning D: Optimizing energy performance 参考答案: A
本题解释: Light pollution reduction does not use a baseline analysis. Interior and exterior lighting equipment should be designed to eliminate light trespass from the site. There is no percentage reduction.
Fundamental Building Commissioning includes the development of the Basis of Design (BOD) document. The BOD must include an informed baseline and focus for validating system\'s energy and environmental performance. This baseline is used as a comparison during when the installation and performance of the commissioned systems are verified. |
|