试卷: LEED AP ID+C 模拟试卷B[查看] A project team is reviewing strategies for retaining stormwater on site for a project that will have a large amount of open space with turf grass. Which strategies will help with retaining stormwater on-site?(choose 3)
A: Building a constructed wetland B: Placing mulch around the areas of turf grass C: Increasing the efficiency of the irrigation system D: Installing cisterns to capture stormwater for irrigation E: Installing bioswales 参考答案: ADE
本题解释: Reference: Sustainable Sites Credit, Site Selection, Stormwater Design-Quantity Control
Keeping stormwater onsite can be done with ponds, wetlands, retention ponds, vegetated filter strips, rain gardens, storing the water onsite for later use, etc.
|
|