LEED GAP

 找回密码
 立即注册

QQ登录

只需一步,快速开始

搜索
查看: 671|回复: 0
打印 上一主题 下一主题

A project design includes an active wastewater treatment system to treat 75% of

[复制链接]

262

主题

0

好友

33

积分

管理员

Rank: 9Rank: 9Rank: 9

跳转到指定楼层
楼主
发表于 2012-7-29 22:19:53 |只看该作者 |倒序浏览
试卷: LEED AP ID+C 模拟试卷B[查看]
A project design includes an active wastewater treatment system to treat 75% of wastewater onsite to achieve Water Efficiency Credit, Innovative Wastewater Technologies. This design decision will impact which project area?
A: Sustainable Sites Credit, Site Selection, Stormwater Design-Quantity Control
B: Sustainable Sites Credit, Site Selection, Stormwater Design-Quality Control
C: Sustainable Sites Credit, Site Selection, Heat Island Effect-Roof
D: Energy and Atmosphere Prerequisite, Fundamental Commissioning of Building Energy Systems

参考答案: D

本题解释:
An active treatment system uses additional energy and requires commissioning, and also measurement and verification. Please note that wastewater is different from stormwater.
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2024-12-23 04:44 , Processed in 0.086523 second(s), 26 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部