试卷: LEED v4 ID+C模拟题C卷英文[查看] A building contractor is finalizing the tasks that must be complete before a building flush-out begins. What task does not have to be completed prior to a building flush-out?
A: Installation of all furnishings B: Installation of all carpet C: Cleaning D: Commissioning 参考答案: D
本题解释: Reference: Indoor Environmental Quality Credit, Construction Indoor Air Quality Management Plan-Befo
Commissioning can take place during the flush-out if no additional contaminants are introduced. Commissioning can also take place after the flush out.
Cleaning, punch-list items, and the installation of furniture and furnishings must be done prior to the flush-out.
|
|