A contractor will install $250,000 of rapidly renewable resources. The project budget is $8.5 million and will have a gross square footage of 230,000. The total materials budget is $4.0 million. How many points can this project earn?
A: 3
B: 0-
C: 2
D: 1

参考答案: D

本题解释:
Materials and Resources Credit Rapidly Renewable Materials

$250,000 / $4,000,000 = 6.25%

5% rapidly renewable materials would earn 1 point.

10% would earn exemplary performance.
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2024-12-23 04:29 , Processed in 0.075020 second(s), 26 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部