A project building on a previously undeveloped site has no setback and will have

[复制链接]

1759

主题

1

好友

5674

积分

管理员

Rank: 9Rank: 9Rank: 9

跳转到指定楼层
楼主
发表于 2012-8-28 19:44:51 |只看该作者 |倒序浏览
试卷: LEED AP BD+C模拟题B[查看]
A project building on a previously undeveloped site has no setback and will have no open
space around the building. What is true about the ability of the project team to achieve
Sustainable Sites Credit, Site Development-Protect or Restore Habitat?
A: The project cannot achieve the credit
B: The project can achieve the credit by installing a green roof that is 20% or larger than the site area
C: The project can achieve that credit by restoring vegetation in a neighboring area at least 2x the building footprint
D: If project also achieves Development Density&Community Connectivity, a vegetated roof can be installed to achieve

参考答案: A

本题解释:
Notes:
The project cannot earn the credit because the site was originally a Greenfield site, and the
building plan has a zero-lot-line (no setback). Since the building consumes the entire site, no
habitat can be protected or restored.
A previously developed site could use a green roof to help earn this credit in combination with SS
Credit 2, but the question states that it is an undeveloped site.
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2024-12-28 03:57 , Processed in 0.076583 second(s), 26 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部