Which of the following would be classified as a soft construction cost?
A: Construction worker labor costs
B: Rental of a dumpster
C: Civil engineer consulting fee
D: Purchase of some steel

参考答案: C

本题解释:
Notes:
A:This is a hard cost. By far the largest portion of the expenses in a construction budget, the hard costs are mostly comprised of the actual construction costs incurred to build the project. Examples of hard costs include masonry, wood, steel, carpet, tile, mechanical systems, roofing.
B:This is a hard cost.
C: A soft construction cost is one that is not directly related to building, construction, etc. These can be architectural, legal, financing, engineering fees, commissioning, and other costs incurred before and after construction.
D:This is a hard cost.
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2024-12-27 11:56 , Processed in 0.074461 second(s), 26 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部