试卷: LEED GA模拟题D[查看] A project team has excluded a section of land in order to meet the requirements of one of the LEED credits. What is true about this action? A: This action would not be allowed under any of the rating systems B: This action is allowed if gross floor area of LEED project is <2% of the gross land area within the boundary C: This action would only be allowed under the LEED for Existing Buildings: Operations & Maintenance rating system D: Certain sections of land can be excluded from site boundary if a responsible party submits a licensed exemption form 参考答案: A
本题解释: Notes:
Reference: LEED 2009 Minimum Program Requirements
A:Land cannot be excluded for the purposes of complying with a credit/prerequisite. This is known as gerrymandering.
B:If the gross floor area is less than 2% of the gross land area within the LEED project boundary the project doesn’t meet the Minimum Program Requirements.
C:No rating system permits this action.
D:The Licensed Professional Exemption Form can be used by a project team’s registered professional engineer, registered architect, or registered landscape architect to submit a streamlined path to certain credits, bypassing otherwise required submittals--O&M introduction |
|