试卷: LEED AP ID+C 模拟试卷A[查看] During fundamental commissioning, who is in charge of developing the basis of design? A: Owner B: Commissioning authority C: Owner and commissioning authority D: Design team 参考答案: D
本题解释: See Energy and Atmosphere Prerequisite, Fundamental Commissioning of Building Energy Systems
The correct answer choice comes from the section titled Step 2, Basis of Design. The design team documents the basis of design, which is the information needed to accomplish the owner's project requirements. These include:
-system descriptions
-IEQ criteria
-design assumptions
-references to codes, standards, regulations, and guidelines
The owner is in charge of developing the OPR, owner's project requirements. |
|