A project team member is verifying that occupants have a connection to the outdo

[复制链接]

1759

主题

1

好友

5674

积分

管理员

Rank: 9Rank: 9Rank: 9

跳转到指定楼层
楼主
发表于 2012-7-30 22:02:08 |只看该作者 |倒序浏览
试卷: LEED AP ID+C 模拟试卷A[查看]
A project team member is verifying that occupants have a connection to the outdoors. The project space is a 5-story office building. What calculations are required to determine if views are available?
A: Measuring at 30 inches above the floor and at a maximum of 5 ft. intervals
B: Measuring direct line of site to perimeter glazing and the horizontal view at a typical seated eye height
C: Measuring at a radius of twice the width of the glazing from the center of the glazing
D: Measuring the window-to-floor ratio

参考答案: B

本题解释:
Reference: Indoor Environmental Quality Credit, Daylight and Views-Views, Implementation

Views require direct line of site to perimeter glazing between 30 inches and 90 inches above the finish floor and a horizontal view at 42 inches.
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2024-12-23 04:07 , Processed in 0.074083 second(s), 25 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部