A project team has purchased several workstations that contain pre and postconsu

[复制链接]

1759

主题

1

好友

5674

积分

管理员

Rank: 9Rank: 9Rank: 9

跳转到指定楼层
楼主
发表于 2012-7-30 10:16:55 |只看该作者 |倒序浏览
试卷: LEED AP ID+C 模拟试卷A[查看]
A project team has purchased several workstations that contain pre and postconsumer content. The workstations cost $1,000 each and are made up of the following: Material Content 100 lbs of steel 90% postconsumer; 30 lbs of plastic 50% postconsumer; 5 lbs Other; What cost can the team attribute to recycled content for each workstation?
A: $770
B: $110
C: $660
D: $900

参考答案: A

本题解释:
Materials and Resources Credit Recycled Content, Calculations

To discover what part of materials cost can be attributed to the recycled material, the cost must be weighted.

Total weight is 135 lbs

100 lb steel X 90% post consumer = 90 lbs / 135 lbs = 66%
66% X $1,000 = $660

30 lbs plastic X 50% post consumer = 15 lbs / 135 lbs = 11%
11% X $1,000 = $110

Total cost of the recycled material is $770.00
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2024-12-23 04:00 , Processed in 0.132979 second(s), 25 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部