LEED GAP

 找回密码
 立即注册

QQ登录

只需一步,快速开始

搜索
查看: 483|回复: 0
打印 上一主题 下一主题

A building has a wind energy system added to the roof. According to the US DOE\\

[复制链接]

262

主题

0

好友

33

积分

管理员

Rank: 9Rank: 9Rank: 9

跳转到指定楼层
楼主
发表于 2012-8-3 09:23:20 |只看该作者 |倒序浏览
试卷: LEED AP ID+C 模拟试卷B[查看]
A building has a wind energy system added to the roof. According to the US DOE’s Commercial Buildings Energy Consumption Survey the estimated electricity the project will use will be 100,000 kWh/year. Energy costs in the area are $8.15/kWh. How much energy must the wind system produce to earn 3 points for the project?
A: $81,500
B: $20,375
C: $40,750
D: $61,125

参考答案: A

本题解释:
To earn 3 points the project must earn Sustainable Sites Credit, Site Selection, On-site Renewable Energy and exemplary performance, which requires 10% renewable energy.

The estimated energy use is 100,000kWh from the CBECS database. This multiplied by the cost per kilowatt hour gives an annual energy cost of $815,000.

$815,000 X 10% = $81,500
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2024-12-23 03:57 , Processed in 0.086347 second(s), 25 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部