试卷: LEED AP ID+C 模拟试卷D[查看] A project anticipates earning both fundamental and enhanced commissioning. Which additional tasks will the commissioning authority need to perform to achieve enhanced commissioning beyond fundamental commissioning?
A: Estimate projected energy savings B: Define a post installation inspection plan C: Review the tenant space operation 8-10 months after final acceptance D: Describe the method of ensuring accurate energy savings determination 参考答案: C
本题解释: Notes:
See Energy and Atmosphere Credit, Enhanced Commissioning, Requirements
Note the differences between what requirements must be met for enhanced commissioning vs. those for fundamental commissioning. Each has six different requirements.
The incorrect answers are taken from what is required for a M&V plan. |
|