试卷: LEED AP ID+C 模拟试卷D[查看] A project team is reviewing the building elements of an existing space that could be reused in a new tenant fit out. The building will be 80% owner occupied. Which items cannot be included in Materials and Resources Credit, Building Reuse-Maintain Interior Nonstructural Components?(choose 2)
A: Floor to ceiling walls B: Subfloor C: Exterior doors D: Built-in cases 参考答案: BC
本题解释: Notes:
This credit requires maintaining existing non-shell, non-structure components, such as walls, flooring, and ceiling.
Exterior doors are part of the shell and are not included.
The subfloor is a structural component and not included. |
|