试卷: LEED AP ID+C 模拟试卷D[查看] An office condominium was built on a site with an existing imperviousness of 36%. The pre-development discharge volume of stormwater is 8,000 gallons. What can the maximum post-development discharge volume be to qualify for Sustainable Sites Credit, Site Selection, Stormwater Design-Quantity Control? A: 4,000 gallons B: 8,000 gallons C: 6,000 gallons D: 2,000 gallons E: 10,000 gallons 参考答案: B
本题解释: Notes:
Note that the question specifically asks for the maximum post-development discharge volume.
The site has an existing imperviousness that is less than or equal to 50%. Because of this, the post-development peak discharge rate and the quantity must not exceed the pre-development peak discharge rate and quantity to meet the requirements of Sustainable Sites Credit, Stormwater Design-Quantity Control, Option 1. The question gave a pre-development discharge rate of 8,000 gallons. The post-development discharge rate would have to be the same or less than this pre-development discharge rate. |
|