试卷: LEED AP ID+C 模拟试卷D[查看] An owner will occupy 80% of a building that is being renovated. The building will have 6 other tenants. What will the project team need to do to earn Energy and Atmosphere Credit, Measurement and Verification? A: Break out the energy costs for the 6 other tenants and exclude the costs from the base rent B: Install continuous metering equipment for lighting systems C: Install submetering equipment D: Separately zone the interior spaces 参考答案: B
本题解释: Notes:
The building is owner occupied, so Option B requirements must be met to achieve the credit.
Continuous metering equipment must be installed for the systems listed in the requirements, including lighting systems.
|
|