试卷: LEED AP ID+C 模拟试卷C[查看] An independent CxA has been hired to help the project achieve Energy and Atmosphere Credit, Enhanced Commissioning. What additional activities will the CxA be required to complete beyond the requirements of fundamental commissioning?(choose 2)
A: Commissioning design review prior to mid-construction docs B: Verify that requirements for training are completed C: Review contractor submittals D: Develop a systems manual E: Implement the commissioning plan 参考答案: AC
本题解释: There are several responsibilities only the CxA can complete for Enhanced Commissioning. Some items can be completed by the CxA or other members of the project team. The question specifically asks for items that the CxA is required to perform. So the correct answers can only be performed by the CxA. |
|