试卷: LEED AP ID+C 模拟试卷C[查看] Which factors are used to calculate the baseline irrigation use for a project?(choose 3) A: Potable water use as determined by water meter bills B: Irrigation efficiency C: Average gallons of irrigation water used D: Species factor E: Density factor 参考答案: BDE
本题解释: See SS Credit 1, Option 2, Path 7, Calculations
The baseline case requires the landscape coefficient using average value that represent conventional equipment and design practices.
The landscape coefficient is used to compute the evapotranspiration rate. To get this value the landscape coefficient must first be computed:
Landscape coefficient = species factor X density factor X microclimate factor. |
|