试卷: LEED AP ID+C 模拟试卷C[查看] A contractor has been hired to verify a M&V plan under post installation conditions. What is a task the contractor needs to do?
A: Implement a commissioning plan B: Review the owner’s project requirements C: Determine the savings resulting from the M&V plan D: Develop a systems manual 参考答案: C
本题解释: Reference: Energy and Atmosphere Credit, Measurement and Verification, Implementation, Step 7
Do not confuse the requirements of M&V with commissioning.
As part of the M&V plan, the savings under the post installation conditions must be determined.
The incorrect choices are tasks required for commissioning.
|
|