A contractor has been hired to verify a M&V plan under post installation conditions. What is a task the contractor needs to do?

A: Implement a commissioning plan
B: Review the owner’s project requirements
C: Determine the savings resulting from the M&V plan
D: Develop a systems manual

参考答案: C

本题解释:
Reference: Energy and Atmosphere Credit, Measurement and Verification, Implementation, Step 7

Do not confuse the requirements of M&V with commissioning.

As part of the M&V plan, the savings under the post installation conditions must be determined.

The incorrect choices are tasks required for commissioning.

分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2025-4-6 23:55 , Processed in 0.075379 second(s), 25 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部