试卷: LEED GA模拟题A[查看] What should the project team do with the LEED Score Card once it has been completed for a new construction project? A: Use it to determine project soft-costs B: Use it to determine the baseline building water use C: Refer to it during the construction process D: Mail it to GBCI 参考答案: C
本题解释: Cost analysis and the bidding process are used for A item;Water calculations are used for B item;The scorecard is used as a reference to make sure the project is on track for the green goals.
The LEED Credit Checklist is also called the LEED Scorecard;Scorecards are not mailed to GBCI.Reference: Sample credit checklist for LEED v3 |
|