A museum is closing down for a period of time while some major renovations occur, and a new
addition is added to the building. What housekeeping tasks must be completed to meet SMACNA
requirements for the IAQ management plan during construction?
A: Clean the project site at least every 24 hours when construction has taken place
B: Using wetting agents for dust
C: Ventilate the construction area at least weekly with outside air
D: Store all porous building materials outside of the construction area until they are needed

参考答案: B

本题解释:
Reference: Indoor Environmental Quality Credit, Construction Indoor Air Quality Management
Plan-During Construction, Implementation, Housekeeping


Using wetting agents for dust is recommended for housekeeping as well as using high efficiency
particulate filters in vacuum cleaners.


Ventilating the construction area helps with Pathway Interruption, not Housekeeping.


While the project must be kept clean more frequently than normal, no specified time period (such
as every 24 hours) is specified.


Porous building materials need to be stored and protected from moisture damage, but they do not
have to be stored outside of the construction area. They should be kept where there are low
humidity levels and protected from water.
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2025-4-20 04:27 , Processed in 0.075332 second(s), 25 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部