Some of the design strategies a project team is proposing include daylighting, d

[复制链接]

1759

主题

1

好友

5680

积分

管理员

Rank: 9Rank: 9Rank: 9

跳转到指定楼层
楼主
发表于 2012-8-12 16:22:18 |只看该作者 |倒序浏览
试卷: LEED AP BD+C模拟题A[查看]
Some of the design strategies a project team is proposing include daylighting, drip irrigation,
photovoltaic systems, optimizing building orientation, and providing high albedo parking surfaces.
The building owner would like to offset some of the higher costs for the sustainable design
strategies being proposed for the building project. What could the design team propose to provide
the greatest reduction to the owner’ s operating costs?
A: Installing net metering
B: Implementing stormwater collection
C: Purchasing RECs
D: Increasing ventilation

参考答案: A

本题解释:
Notes:


Net metering is a billing and metering arrangement that lets buildings with on-site renewable
energy redirect excess energy to the local power grid. This excess electricity can then be deducted
from what the building draws from the grid for electricity use.


Increased ventilation can increase costs, because more air then needs to be distributed in the
building.


RECs are for green power and would not lower costs as much as net metering.


Stormwater collection will help reduce water consumption for irrigation. However water is very
cheap relative to electricity and the offset in costs would thus be less than for net metering.
Additionally because drip irrigation is already being used, a savings of 30%-50% in water use
already exists. Less water also requires less energy to distribute.
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2025-4-20 15:21 , Processed in 0.083667 second(s), 25 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部