A project team is attempting Indoor Environmental Quality Credit, Construction Indoor Air
Quality Management both During Construction and Before Occupancy. The contractor will be
using air quality testing to determine if contaminant levels have not been exceeded. What should
occur after the final cleaning and before the baseline IAQ testing has begun?(choose 2)
A: Installing furnishings
B: Replacing all filtration media with MERV 13 filters
C: Air testing and balancing of the HVAC system
D: Completing punch list items

参考答案: AC

本题解释:
Notes:


Reference: Indoor Environmental Quality Credit, Construction Indoor Air Quality Management
Plan-Before Occupancy, Implementation, Air Quality Testing


Tune the HVAC system before any air testing begins. This way the air being measured is the same
air occupants will be breathing.


Install interior fixtures and furnishings. It is not required to install movable furnishings like
workstations but it is recommended. These furnishings will likely have some off gassing.


Replace filtrating media. MERV 8 filters can be used for this process - MERV 13 filters are not
required. Consider using MERV 13 filters if the project will also be attempting Indoor
Environmental Quality Credit 5, Indoor Chemical and Pollutant Source Control.


Punch list items should be completed before the final cleaning so as to not add additional dirt,
contaminants, etc. to the indoors.
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2024-12-25 22:53 , Processed in 0.078823 second(s), 25 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部