试卷: LEED AP BD+C模拟题D[查看]
For projects that will record indoor light measurements to determine daylight illumination
levels, what must the project team include in the design?
A: Daylight redirection and/or glare control devices
B: Sunlight redirection
C: View-preserving automated shades
D: Increased glazing

参考答案: A

本题解释:
Notes:
Reference: Indoor Environmental Quality Credit, Daylight and Views-Daylight ,
Requirements, Option 3
Glare control or daylight redirection is required because it can hinder visual tasks in high
contrast situations.
The only exceptions are areas where tasks are performed that could be hindered by
daylight, but the team will have to explain why these areas are excluded.
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2024-12-25 22:51 , Processed in 0.077598 second(s), 25 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部