LEED GAP

 找回密码
 立即注册

QQ登录

只需一步,快速开始

搜索
查看: 345|回复: 0
打印 上一主题 下一主题

The project team for an elementary school did not perform a whole building simul

[复制链接]

1759

主题

1

好友

5674

积分

管理员

Rank: 9Rank: 9Rank: 9

跳转到指定楼层
楼主
发表于 2012-8-12 18:42:55 |只看该作者 |倒序浏览
试卷: LEED AP BD+C模拟题D[查看]
The project team for an elementary school did not perform a whole building simulation for
Energy and Atmosphere Credit, Optimize Energy Performance. Instead the team is
estimating 6.6kWh/SF/year of energy use for the 98,750 SF building. The project team is
expecting to pay $7.74/kWh for renewable energy. How much energy must be purchased
to earn an exemplary performance point for Energy and Atmosphere Credit, Green
Power?
A: $1,765,590
B: 1,303,500 kWh
C: $5,044,545
D: 651,750 kWh

参考答案: B

本题解释:
Notes:
To earn exemplary performance, the team must purchase 100% energy from renewable
energy sources.
The team must find the total annual energy use.
6.6kWh/SF/yr * 98,750 = 651,750kWh/yr
The project must purchase this amount for two years.
651,750kWh/yr *2 = 1,303,500kWh is the amount that must be purchased to earn
exemplary performance.
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2024-12-26 11:02 , Processed in 0.075496 second(s), 25 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部