LEED GAP

 找回密码
 立即注册

QQ登录

只需一步,快速开始

搜索
查看: 275|回复: 0
打印 上一主题 下一主题

A school project is near rural farmland. The project site was previously a retai

[复制链接]

1759

主题

1

好友

5674

积分

管理员

Rank: 9Rank: 9Rank: 9

跳转到指定楼层
楼主
发表于 2012-8-12 18:42:55 |只看该作者 |倒序浏览
试卷: LEED AP BD+C模拟题D[查看]
A school project is near rural farmland. The project site was previously a retail location.
The site area is large and equals 500,000SF while the building footprint will only be
50,000 SF. A majority of the area will be restored with native and adaptive plants. Water
runoff methods will include cisterns, vegetated swales, and open grid paving. Open grid
paving takes up 30,000 SF. What is the minimum amount of land that could be restored to
earn sustainable site credit, Site Development - Protect and Restore Habitat to earn an
exemplary performance point?
A: 135,000 SF
B: 450,000 SF
C: 420,000 SF
D: 337,500 SF

参考答案: D

本题解释:
Notes:
To earn exemplary performance point for SS Credit 5.1 the project must restore 75% of
the site excluding the building footprint or 30% of the site including the building footprint,
whichever is greater.
(500,000SF - 50,000) *.75 = 337,500
500,000 * 0.3 = 150,000
The minimum amount the project can restore to earn exemplary performance is 337,500.
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2024-12-26 10:36 , Processed in 0.088242 second(s), 25 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部