试卷: LEED AP BD+C模拟题D[查看] A renovation project will have 50 tons of demolition debris. Of the construction waste, 5
tons can be donated, 15 tons can be recycled, and 5 tons will be reused on-site. Which
statements are true regarding this project’s certification?(choose 2) A: The project cannot earn Construction Waste Management because the donated materials do not count as the waste diverted B: The 5 tons of reused material can’t contribute to Materials Reuse if material is include in Construction Waste Management C: The project would earn one point for Materials and Resources Credit, Construction Waste Management D: The recycled material would count toward Materials and Resources Credit, Recycled Content 参考答案: BC
本题解释: Notes:
The project is diverting 25 tons (5 donated, 15 recycled, 5 reused) from the waste stream,
so one point can be earned for Construction Waste Management. MR Credit 2
Construction Waste Management can earn 1 pt for 50% recycled or salvaged waste.
The 5 tons of reused material cannot contribute to Materials Reuse if the materials are
included in Construction Waste Management. See MR Credit 3, Reused Materials Found
Off-Site. Materials qualifying for MR Credit 3 cannot be applied to MR Credits 1, 2, 4, 6 or