试卷: LEED GA模拟题E[查看] What needs to occur to have an integrated team?
A: Regular meetings of all key project members B: Regular meetings of only the owner, architect, and contractor C: Durability planning D: Quarterly meetings between engineers 参考答案: A
本题解释: A:Regular meetings of all key project members and the ability to call emergency meetings if a decision must be made quickly are both needed for project team decision making.
B:All team members must be involved with regular meetings to have an integrated team.
C:Durability planning would be one part of the discussions the integrated team would have.
D: Quarterly meetings between engineers would not be frequent enough. |
|