The project team for an elementary school did not perform a whole building simul

[复制链接]

1759

主题

1

好友

5674

积分

管理员

Rank: 9Rank: 9Rank: 9

跳转到指定楼层
楼主
发表于 2012-8-28 19:44:51 |只看该作者 |倒序浏览
试卷: LEED AP BD+C模拟题C[查看]
The project team for an elementary school did not perform a whole building simulation for Energy and Atmosphere Credit, Optimize Energy Performance. Instead the team is estimating 6.6 kWh/SF/year of energy use for the 98,750 SF building. The project team is expecting to pay $0.07/kWh for renewable energy. How much energy must be purchased to earn Energy and Atmosphere Credit, Green Power?
A: $15,967
B: 228,112 kWh
C: 456,225 kWh
D: $31,935

参考答案: C

本题解释:
Notes:
Reference: Energy and Atmosphere Credit, Green Power, Requirements
To earn this credit the team must purchase 35% energy from renewable energy sources.
The team must find the total annual energy use.
6.6 kWh/SF/yr X 98,750 = 651,750 kWh/yr
651,750 kWh/yr X 35% = 228,112 kWh/yr
The project must purchase this amount for two years.
228,112 kWh/yr X 2 = 456,225 kWh is the amount that must be purchased to earn the Green Power credit.
Green power purchases are based on the quantity of power purchased not on cost.
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2024-12-27 12:54 , Processed in 0.072964 second(s), 25 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部