The contractor for a building that will house city employees will try to meet th

[复制链接]

203

主题

0

好友

512

积分

超级版主

Rank: 8Rank: 8

跳转到指定楼层
楼主
发表于 2012-8-28 19:44:51 |只看该作者 |倒序浏览
试卷: LEED AP BD+C模拟题D[查看]
The contractor for a building that will house city employees will try to meet the SMACNA
guidelines for Indoor Environmental Quality Credit, Construction Indoor Air Quality
Management Plan-During Construction. What aspects does the contractor need to document to achieve this credit?(choose 2)
A: On-site absorptive materials were protected from moisture damage
B: A building flushout with a total air volume of 14,000 cu. ft. per sq. ft. per floor was used
C: MERV 8 filtration media was used for permanently installed air handlers
D: MERV 13 filtration media was used for temporary air handlers

参考答案: AC

本题解释:
Notes:
Reference: Indoor Environmental Quality Credit, Construction Indoor Air Quality
Management Plan-During Construction, Requirements
For this credit:
-Meet SMACNA guidelines
-Protect absorptive material (stored and installed) from moisture damage
-Use MERV 8 filters for permanent air handlers
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2024-12-28 04:38 , Processed in 0.078404 second(s), 25 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部